These are for guide purposes only. Always read the manufacturers recommendations and use professional installers.

  • Humidity of the environment should be within the range of 40 – 60%
  • Wall moisture content should be 2%
  • Screed moisture content shouldn’t exceed 1.5%
  • Room temperature should be between +18° - +24°C
  • Sub-floor screen temperature should be between +18° - +21°C
  • Only unpack the floor planks immediately before installation
  • Use glue that doesn’t contain water
  • Leave a gap of 1-1.5cm from the walls
  • If you have underfloor heating, don’t switch the heating on for at least 3 days
  • Only raise the heating temperature by 2°-3°C a day
  • Maximum heating temperature cannot exceed +28°C

To ensure maximum stability, our recommended installation method is glue planks all the bottom down to a sub-floor.